Transneft Upper Volga Completes Revamping Surgut – Polotsk Oil Trunk Pipeline Section

Date of publication: 18 March 2019 Print

Transneft Upper Volga has completed the revamping of the Surgut – Polotsk oil trunk pipeline (OTP) in Bogorodsky District of Nizhny Novgorod Region. 

The works were conducted in compliance with the development, technical upgrading and revamping programme covering Transneft Upper Volga’s trunk pipelines facilities. 

The revamping of the OTP section began in July 2018. A planned replacement of 1.83 km of the pipeline was performed.

The goal is to increase reliability and ensure uninterrupted oil transportation through the Transneft oil trunk pipelines.  

After the completion of the set of measures, Transneft Upper Volga  performed the technological connection of the reconstructed line section to the existing oil trunk pipeline.

Transneft Upper Volga Press Service